How Long Does a Kitchen Installation Take?

6 min read 6 sections

A full kitchen installation takes 5 to 10 working days. A day-by-day timeline, what makes one run longer, and how long you are without a cooker.

In short: A full kitchen installation takes 5 to 10 working days from strip-out to handover. A like-for-like replacement in the same layout is at the short end. Moving the sink, cooker or a wall, or replacing the flooring throughout, pushes it to 15 working days or more. The single biggest delay is not the fitting — it is stone worktops, which cannot be templated until the units are in and then take a further 10 to 14 days to come back.

What's in this guide 6 sections
  1. How long does a kitchen installation take?
  2. A day-by-day kitchen installation timeline
  3. How long different kitchens take
  4. What makes a kitchen take longer?
  5. How long will you be without a kitchen?
  6. Do you need building regulations approval for a new kitchen?

01 How long does a kitchen installation take?

A kitchen installation is defined as the sequence from stripping out the old kitchen to handing back a working room with services connected, appliances in and worktops fitted. For a standard family kitchen in the same layout, that takes 5 to 10 working days.

The number people are usually given — "about a week" — is true of the fitting itself and untrue of the project. If you are having stone or quartz worktops, the room is not finished in a week under any circumstances, because those worktops are cut to a template taken from your installed units and take another 10 to 14 days to arrive. That is not a delay, it is how the material works, and any quote that hides it is setting you up for a bad surprise.

02 A day-by-day kitchen installation timeline

This is a typical ten-day run for a kitchen with a changed layout and laminate worktops. A like-for-like swap compresses days 2 to 4 into one.

  1. Day 1 — Strip out. Old units, appliances, worktops, tiling and flooring come out. Services are capped off safely. The room is left as a shell.
  2. Day 2 — First fix plumbing and electrics. New pipework and cabling run to where the sink, dishwasher, washing machine, hob, oven and sockets are actually going. This is the day that decides whether the finished kitchen works.
  3. Day 3 — Plastering and making good. Walls patched or reskimmed where units and tiling came off, and any new stud or boarding built.
  4. Day 4 — Flooring, where it goes under the units. Floor levelling if the room needs it.
  5. Days 5 to 7 — Base units set and levelled, wall units hung, end panels and cornice fitted. On day 7 the room finally looks like a kitchen.
  6. Day 7 — Worktop templating, if you are having stone or quartz. The template is taken from the installed units, so it cannot happen earlier.
  7. Day 8 — Laminate worktops cut and fitted, or a 10 to 14 day wait begins for stone.
  8. Day 9 — Second fix. Sink and taps plumbed in, appliances connected and tested, sockets and switches fitted, extractor ducted.
  9. Day 10 — Tiling or splashbacks, silicone, handles, plinths, final adjustments to doors and drawers, clean and handover.

With stone worktops, days 9 and 10 happen after the stone lands, so the calendar runs to roughly three weeks even though the working days do not change.

03 How long different kitchens take

Type of jobWorking daysCalendar time with stone tops
Doors and worktops only (refacing)2–3 days2–3 weeks
Like-for-like replacement, same layout5–7 days3 weeks
New kitchen, changed layout8–12 days3–4 weeks
Kitchen plus utility room12–15 days4–5 weeks
Kitchen with a wall removed15–20 days5–6 weeks
Kitchen-diner extension fit-out20 days+6 weeks+
Handleless dark blue cabinet doors and a built-in oven housing
Our own work — kitchens, North Derbyshire.

04 What makes a kitchen take longer?

Almost every overrun on a kitchen comes from one of these six things, and five of them are knowable before anyone starts.

  • Stone or quartz worktops — 10 to 14 days between template and fit, every time. Plan around it rather than hoping.
  • Moving the sink or the soil connection. Drainage has to fall, so relocating a sink across a room can mean lifting floors.
  • Removing a wall. Structural work brings in a steel, building control and drying time, and it happens before the kitchen starts, not during.
  • Appliances that arrive late or arrive wrong. An integrated appliance in the wrong size stops a run of units dead.
  • Old houses. Walls that are 30mm out of plumb over a 3-metre run need scribing and packing, and that is slow, careful work.
  • Waiting on other trades. This is the one that is genuinely avoidable, and it is why we do not subcontract: a kitchen that stops for four days waiting on an electrician has not got faster, it has got longer.

05 How long will you be without a kitchen?

You lose the sink and the cooker from day 1 and get them back on day 9, so expect around 7 to 9 days without a working kitchen on a standard job. With stone worktops it is longer, because the sink cannot go in until the worktop does.

The practical answer is to set up a temporary kitchen elsewhere before we start — kettle, microwave and fridge in another room, and washing up in the bathroom. We will tell you which day the water goes off and which day it comes back, and we reconnect the washing machine at the end of the day wherever it is possible to do so.

If you have a utility room with a sink, say so at the survey. We can often sequence the work so the utility stays live the entire time, which changes the experience of the fortnight completely.

06 Do you need building regulations approval for a new kitchen?

Replacing a kitchen in the same layout does not need building regulations approval or planning permission. It is a like-for-like refit of an existing room.

Building regulations do apply when you add or move electrical circuits, alter drainage, install a new gas appliance, remove a structural wall, or replace a window. In practice most kitchens trigger Part P for the electrical work, which is notifiable and must be certified. Ventilation requirements also apply — a kitchen needs mechanical extraction, ducted outside rather than recirculating, wherever that can be achieved.

Tall oven housing and lit worktop in a handleless dark blue kitchen
Our own work — kitchens, North Derbyshire.

Reading up before you commit is exactly the right order to do this in. When you are ready, the quote is free.

Good to know

Frequently Asked Questions

How long does a small kitchen take to fit?
A small galley or single-run kitchen of six to eight units typically takes 4 to 6 working days in the same layout, with laminate worktops. The saving over a larger kitchen is smaller than people expect, because the sequence is identical — strip out, first fix, plaster, units, second fix, finish — and only the unit-setting days shorten.
Why do quartz worktops take so long?
Quartz and stone worktops are cut to a physical or laser template taken from your units after they are installed and levelled, because a millimetre of error in the template is a millimetre of gap against your wall. Once templated, the slab is cut, the sink and hob apertures machined and the edges polished, which takes 10 to 14 days at most fabricators. Laminate worktops are cut on site and add no wait at all.
Can I stay in the house during a kitchen installation?
Yes, almost everyone does. You lose the sink and cooker for about a week and there is dust during strip-out and plastering, but the rest of the house stays usable. We sheet routes through the house, keep the work to one room and clear up at the end of each day. Kitchens are noisier than bathrooms but far less disruptive to live around than people expect.
What order should a kitchen be fitted in?
Strip out, first fix plumbing and electrics, plastering, flooring under the units, base and wall units, worktop template, worktops, second fix, then tiling and finishing. The order matters because each stage buries the one before it — first fix pipework disappears behind plaster, and plaster disappears behind units. Doing them out of sequence means undoing finished work.
Free, no-obligation quote

Want a Fixed Price for Your Own Project?

We visit, measure up, look at what's actually behind the walls, and give you a written quote with the exclusions stated plainly. Free, and no obligation.

Much of our work comes from repeat customers and recommendations, reflecting the standard we work to.

Call now WhatsApp Free quote